The LRT Line 2, a thirteen-station, 17.6-kilometer line was the third rapid transit line to be built in Metro Manila when it started operations in 2003.
The catenary system is an essential component of the electric rail system, consisting of overhead wires, poles, and associated hardware that provide power to the train.
First Balfour worked under supervision of Balfour Beatty Rail for the installation of catenary works system for LRT Line 2.
Still under supervision of BB Rail, the scope also includes the supply of off shore equipment, installation of new substation equipment, and railway electrification requirement at 1500 V DC.
Capacity: 1,500V DC